Palmetto Vermiculite Grade C 3 is a medium particle size material meeting ASTM C516 Type 1, Grade 3 specifications. The material is widely used as a component in growing media for professional growers. The Greenhouse Industry uses large quantities of this material as a component of soil mix media for growers. The unique properties improve moisture retention and soil aeration and when mixed with bark provides a ood growing medium for plant propagation performance.
Vermiculite is the geological name given to a group of hydrated, laminar minerals which are aluminum-iron-magnesium silicates,resembling mica in appearance. When exposed to intense heat, the material expands or exfoliates. Exfoliated vermiculite has several unique properties which have industrial applications and account for its commercial value. These properties include, low thermal conductivity, high water holding capacity, incombustibility, and insolubility in both water and organic solvents.
The time required to build an average pool start to finish is about 100 to 120 man hours (3 people x 40 hours). 3 subcontractors are normally required. They are: The excavator to dig the pool, The licensed electrician to wire the pump and light, and the Concrete Finishers (if you choose to pour a concrete deck). All other work can be done by any average handyman using our instructional video and manual. Simple tools and common sense are all that is required. (and the nerve to dig up your backyard).
Call your local municipality and find out what is required as far as fencing, property line, sewer, drainage and electrical code requirements for your area. Utility companies will locate power, gas, telephone and cable lines free of charge. Locate your septic tank and drain fill lines. The drain fill lines can be relocated if needed. Use flour or spray paint to mark the swimming pool location in your yard. Obtain the required permits before starting your pool installation.
Depending on where you are located, the pool kit will be delivered by our driver on our truck, or delivered by one of our partnering truck lines. Plan on having at least 2 people to help unload the truck. Inspect the shipment to be sure everything on the list is there and in good condition. Watch the installation video several times to become familiar with the construction process.
Day 1: Many pool companies, even well established ones, subcontract the dig to an excavation contractor. Most contractors use a backhoe to dig pools. Look in your local yellow pages, and ask around to find out who digs for the pool companies in your area. Look under excavating contractors, or septic tank contractors. Pools can also be successfully dug with a rented skid steer loader.
Day 2: Bolt together, Align, and Level the wall panels and braces. Pour the concrete footer if required. Pull strings and hand trim the inside of the pool to prepare for the vermiculite and cement floor. Install the Skimmer and return fittings on the pool wall. Install the Aluminum coping with the self tapping screws provided. Connect the PVC schedule 40 plumbing to where the pump and filter will be located.
Day 3: The easiest and best floor material is premixed vermiculite and cement. We also sell pure vermiculite that can be mixed with Portland cement. You can buy portland cement locally to save on freight. Rent a 5 cubic foot morter mixer (with rotating paddles inside the drum). Three or four people can easily trowel the pool bottom in 4 or 5 hours. You can mix material and work at your own pace.
Day 4: The vermiculite bottom should be dry enough to walk on now. Walk down into the pool and touch up any rough places. Inspect and sweep the entire floor. Lay the liner box in the pool and unfold the liner. Install the liner bead into the coping starting with the shallow end corners. Place the hose from one or two shop vacs behind the liner to suck the air out and remove wrinkles.
Day 5: Fill the pool with water using a garden hose. With normal water pressure, city water will fill an average 18 x 36 pool in about 48-72 hours. Start backfilling around the outside of the walls. We backfilled by hand using shovels and wheelbarrows for years. (thanks, Dad) Most people rent or contract a bobcat skid steer loader. As the water comes up on the wall, place about 10 inches of dirt behind the wall and dampen and pack with your feet or a hand tamp. Continue to do this in 10 inch increments as the water comes up on the wall. Form the area you want for the concrete deck, or prep the area for pavers or wood deck. Set the ladder, handrail and dive equipment.
The pump and light are wired 110 volt. Depending on the electrical code in your area, this may have to be done by a licensed electrician. Plumbing the pump and filter is very simple and usually takes about an hour.
Day 6: As with the excavation, most pool companies subcontract the concrete finishing to concrete finishers. Find a crew that is used to doing swimming pools. You may also choose to lay brick or concrete pavers yourself. That’s it! Clean up and throw out grass seed. Enjoy your new pool!